17.12 Change Order #3B Between Mountain View Los Altos High School District and McKim Corporation to Provide Services Related to the Mountain View High School Student Services Building Project |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
Mountain View Los Altos High School District is requesting Change Order #3B with McKim Corporation be ratified: - Demolish concrete in the parking lot in order to allow for base rock and asphalt to meet the finish grade in the staff parking lot. This is an unforeseen condition and will be tracked using time and materials. - Remove rock that was placed around the building prior to winter in order to prevent dirt run off during the rainy season. This work is to be completed via time and materials. |
|
|
Funding:
|
$37,850.81 Bond (change order is within budget) |
|
|
Recommendation
|
Ratify Change Order #3B between Mountain View Los Altos High School District and McKim Corporation to provide services related to the Mountain View High School Student Services Building project. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Irene Aguilar - Administrative Assistant |
|
Signed By: |
|
Mike Mathiesen - Associate Superintendent |
|
Signed By: |
|
Nellie Meyer - Superintendent |
|
|
|
|
|
|
|